Question 1 The issue log is an output from which
process?
a) Manage
Stakeholder Engagement
b) Monitor
and Control Project Work
c) Control
Communications
d) Control
Stakeholder Engagement
Question 2 Work performance information:
Incorrect
Response
a) is work
performance data.
b) requires
discussion and dialogue.
c) organizes
and summarizes the performance data.
d) communicates
the right message.
Question 3 The tools and techniques for the
Control Communications process include:
a) expert
judgment.
b) information
management systems.
c) meetings.
d) all of
these.
Question 4 The key benefit of Control Stakeholder
Engagement Process is it will:
a) facilitate
consensus toward project objectives.
b) influence
people to support the project.
c) modify
organizational behavior to accept the project outcomes.
d) maintain
or increase the efficiency and effectiveness of stakeholder engagement.
Question 5 Performance reporting includes:
a) status
reports.
b) progress
measurements.
c) forecasts.
d) all of
these.
Question 6 The
purpose of status meetings is to:
a) exchange project information.
Incorrect
Response
b) review the work performance data.
c) issue
change requests.
d)
enact
decision making.
Question 7 Where
would you find a stakeholder’s classification?
a) Stakeholders engagement assessment matrix
b) Stakeholder
register
c) Power/interest grid with stakeholders
d) Stakeholder salience model
Question 8 The main output of the identify
stakeholders process is the:
a) stakeholder
register.
b) power/influence grid.
c) stakeholder management plan.
d) salience model.
Question 9
The
appropriate strategy for a high-power / low-interest stakeholder is:
Incorrect
Response
a) keep
informed.
b) keep
satisfied.
c) manage closely.
d) monitor.
Question 10
Managing stakeholder engagement may result in:
a) change requests.
b) preventative actions.
c) corrective actions.
d) all of
these.