Saintleo PRM520 Module 2 Discussion Latest 2019 MAY Question # 00601199 Subject: Education Due on: 05/11/2019 Posted On: 05/11/2019 11:46 AM Tutorials: 1 Rating: 4.8/5
PRM520 Monitoring, Controlling, and Closing Projects
Module 2 Discussion
The
Situation: You have been hired as the project manager to construct a custom
home. The owners have asked for some “minor changes” such as relocating two
electrical outlets, adding a refrigerated wine cabinet that will require an
electrical connection, and adding gutters to the outside of the house. The
owners have seen the price list for these changes and are agreeable. The owners
also requested that an internal wall be relocated. Unfortunately, the wall is
load bearing which means that the architect and structural engineer must modify
the plans and the local building department must approve the modified plans.
The key members in your project team are the architect, structural engineer,
and framing subcontractor. The redesign by the architect and engineer will take
about two weeks. The building department needs two weeks after you submit the
revised plans. You don’t have a price for the relocated wall.
The Assignment:Refer to Section 5.6 of the
PMBOK® Guide. Prepare a response consisting of a minimum of 500 words. Describe
how you would perform control scope and prepare change requests for the Perform
Integrated Change Control process. Include at least three credible references
in addition to the PMBOK® Guide with at least one of these being a
peer-reviewed journal article. Properly cite your response.