EVM Assessment – The program level Integrated Baseline Review
EVM Assessment
EVM Assessment
1. The program level Integrated Baseline Review (IBR) is conducted for which performing organization
_____ a) The Prime Contractor
_____ b) The client Program/Product Manager
_____ c) The sub-contractor
___ d) All of the above
2. The purpose for conducting an Integrated Baseline Review (IBR) is to
_____ a) lay a solid foundation for mutual understanding of risk
_____ b) define the tools, processes and procedures for Earned Value Management (EVM)
______c) integrate traditional program management processes with technical measures
_____ d) establish a management control point for cost, schedule and technical performance
3. The Organizational Breakdown Structure (OBS) is a key process artifact used to organize the program because:
_____ a) The OBS must be exactly the same as the Organization Structure
_____ b) The OBS defines the organization that will manage and oversee the work done under contract
_____ c) The OBS defines specific resources down to individual work assignments
_____ d) The OBS is a functionally organized grouping of participating organizations
4. Earned Value Management practices for the U.S government are defined by:
_____ a) OMB Circular A-11
_____ b) The Federal Acquisition Regulation (FAR)
_____ c) The NDIA Intent Guide, based on the EIA-748 standard
_____ d) All of the above
5. The Schedule Performance Index (SPI) measures
_____ a) The value of work accomplished (EV) against the planned value of work (PV)
_____ b) The value of the actual cost (AC) against the planned value of work (PV)
_____ c) The cumulative value of work accomplished (EV) against the cumulative actual cost (AC)
_____ d) None of the above
6. The Earned Value methodology uses these core metrics to calculate program performance:
_____ a) Planned value (PV), earned value (EV), and actual costs (AC)
_____ b) Cost variance (CV), schedule variance (SV), and variance at completion (VAC)
_____ c) Cost performance index (CPI) and schedule performance index (SPI)
_____ d) Estimate to complete (ETC) and to complete performance index (TCPI)
7. You have been hired to plant trees for 10 days. You are supposed to plant 10 trees per day and you are paid $10 for each tree planted. After 4 days, you planted 50 trees and you were paid $500. What are the SPI and CPI for the project?
_____ a) SPI=0.8, CPI=1.0
_____ b) SPI=1.25, CPI=1.0
_____ c) SPI=1.0, CPI=0.8
_____ d) SPI=1.0, CPI=1.25
8. Which IPMR format is a narrative report used to explain significant cost and schedule variances and other identified contract problems and topics?
_____ a) Format 1
_____ b) Format 3
_____ c) Format 4
_____ d) Format 5
9. Which of the following is one of the Integrated Program Management Report (IPMR) formats?
_____ a) Format 8 – Responsibility Assignment Matrix (RAM)
_____ b) Format 9 – Contract Budget Base (CBB)
_____ c) Format 5 – Explanations and Problem Analysis
_____ d) All of the above
10. When budget value earned with elapsed time and is always equal to the monthly planned value
describes which earned value technique?
_____ a) Weighted Milestone
_____ b) Level of Effort
_____ c) Percent Complete
_____ d) Apportioned Effort
11. Work that “cannot be measured” or is characterized as indirect, supporting or sustaining work is
measured by which earned value technique?
_____ a) Weighted Milestone
_____ b) Level of Effort
_____ c) Percent Complete
_____ d) Apportioned Effort
12. A program manager who is concerned about how efficiently the program is meeting cost and
schedule objectives should look principally at
_____ a) Percent Spent and Percent Complete
_____ b) Cost Variance, Schedule Variance and Variance At Complete
_____ c) Cost Performance Index and Schedule Performance Index
_____ d) Variance Analysis
EVM Assessment
Student Name:
13. A cost performance index (CPI) greater than 1.0 indicates:
_____ a) Favorable cost performance
_____ b) Unfavorable cost performance
_____ c) Neutral cost performance
_____ d) None of the above
14. Which of the following process artifacts s considered to be the foundation for defining project
scope, developing plans and reporting program status?
_____ a) Responsibility Assignment Matrix (RAM)
_____ b) Organization Breakdown Structure (OBS)
_____ c) Work Breakdown Structure (WBS)
_____ d) Business Case Analysis Report (BCAR)
15. A Work Breakdown Structure (WBS):
_____ a) Ensures all work is identified and defines “what” the program is doing
_____ b) Provides the project sponsor with a time-phased task summary
_____ c) Allocates cost to work packages
_____ d) Assigns responsibility and instills accountability
16. The Responsibility Assignment Matrix (RAM) integrates the:
_____ a) the project OBS and WBS
_____ b) the budget and Control Accounts
_____ c) the project scope and schedule.
_____ d) Control Accounts and the manager.
17. Which is NOT an example of earned value management (EVM) graphical trend analysis?
_____ a) Estimates at complete (EAC)
_____ b) Cost performance Index (CPI)
_____ c) Risk cost performance index trend
_____ d) Cost and schedules variances
18. Your project has entered the detail design phase. The engineering manager tells you that your
senior engineer will be leaving the program in 1 month to work on a troubled project for several
months. You should:
_____ a) Anticipate that will have to report both a cost and schedule variance for the time that your
senior engineer is not available.
_____ b) Ask the senior engineer if she can work overtime on your project without charging her time
because she can charge her normal time to the other project.
_____ c) Revise your ETC downward since you will not have to pay the engineer’s salary
_____ d) Revise your ETC upward since you need to replace the senior engineer and train the new
person
19. The project’s major subassembly has failed its acceptance test. The next step should be to
_____ a) Compute an EV based EAC to determine the cost of additional testing
_____ b) Determine the cause of the failure and perform replanning to address the work required
_____ c) Transfer the BCWP (EV) for conducting the test in the next month’s report
_____ d) Increase the BCWS (PV) for the test since it was more difficult than planned
20. After schedule update, the float is computed to be less than zero (i.e., negative float). This tells
you that
_____ a) The project will complete late unless action is taken to recover the schedule
_____ b) The project team can take some time off
_____ c) The critical path work is ahead of schedule but the other work is behind schedule
_____ d) The most recently completed task took less time than planned
21. A control account has a negative cost variance (CV) of 550 staff hours. Which of the following
statements is TRUE?
_____ a) The control account is not using EVM because the CV is in staff hours and should be
calculated in dollars
_____ b) The staff hours should be converted to dollars using direct labor rates
_____ c) The control account has too many people assigned
_____ d) The control account CPI will be less than 1.0
22. The Control Account Manager (CAM) is responsible for maintaining the CAM notebook which
contains the following elements:
_____ a) Programmatic records that provide a history of the Control Account, including EV process
artifacts
_____ b) The IMP, the IMS, the execution level schedule, the milestone schedule, and the risk
schedule
_____ c) The Quality Management Plan
_____ d) The Program Management Information System (PMIS)
23. The _________ is the authorizing document that serves as the agreement between the program
manager and the Control Account Manager (CAM):
_____ a) contract
_____ b) Responsibility Authorization Document (RAD)
_____ c) Baseline Change Document (BCD)
_____ d) Work Authorization Document (WAD)
24. The responsibilities of the Control Account Manager (CAM) include:
_____ a) Establish and maintain detailed schedules and cost plans
_____ b) Monitor performance and assess earned value
_____ c) Perform day-to-day management of the control account
_____ d) All of the above
25. A control account is a major control point for:
_____ a) cost summation
_____ b) scope description
_____ c) variance analysis and reporting
_____ d) all of the above
26. The benefits derived from using an EVMS to manage major programs include
_____ a) Facilitates improved planning
_____ b) Provides for objective measurement of work accomplishment
_____ c) Managers are better able to identify appropriate resources to accomplish the work
_____ d) All of the above
27. A project’s Performance Measurement Baseline (PMB) includes which of the following?
_____ a) Control Accounts
_____ b) Undistributed Budget
_____ c) Management Reserve
_____ d) A and B
28. The Performance Measurement Baseline can only be changed:
_____ a) when the Estimate To Complete (ETC) changes
_____ b) by anyone desiring Management Reserve (MR) to cover a loss
_____ c) through formal change control procedures
_____ d) None of the above
29. Which of the following is NOT a component of the Performance Measurement Baseline?
_____ a) Control Accounts
_____ b) Undistributed Budget
_____ c) Management Reserves
_____ d) Planning Packages
30. EVM “triple constraints” are:
_____ a) Schedule, cost, and requirements
_____ b) Cost, schedule, and risk
_____ c) Cost, scope/performance, and schedule
_____ d) Schedule, resource, and cost
31. In support of the program management and EVM, the accounting system must:
_____ a) perform financial accounting according to GAAP standards
_____ b) obtain information for performance management purposes
_____ c) accumulate costs at the control account or lower of the WBS
_____ d) both a and c
32. Earned Value formulas and indices provide:
_____ a) variance analysis
_____ b) measures of project health with respect to cost, schedule, and technical performance
_____ c) the fundamental cause of the variance
_____ d) recommended corrective action
33. Which function is not one of the elements of the Earned Value Management Process?
_____ a) Organization
_____ b) Planning, Scheduling, and Budgeting
_____ c) Revisions and Data Maintenance
_____ d) Legal contract reviews
34. Retroactive changes
_____ a) should only be allowed in extraordinary circumstances.
_____ b) define how much money was charged to the project.
_____ c) are allowed at any time for any reason.
_____ d) control how baseline changes are incorporated
35. Baseline changes may occur as the result of all of the following except:
_____ a) contractual changes/modifications
_____ b) application of undistributed budget
_____ c) the use of management reserve
_____ d) to eliminate reporting of legitimate overruns
36. The _______________ lays out the total scope of the project from beginning to end, down to the
control account level, and includes key milestones and decision points:
_____ a) Detail schedule
_____ b) Supplementary schedule
_____ c) Integrated Master Schedule
_____ d) Master Plan
37. You can find key information about industry and government best practices for EVM in the
following documents
_____ a) GAO Cost Estimating Guide
_____ b) NDIA EVM Implementation Guide
_____ c) Mil Std 881
_____ d) All of the above
38. The programmatic management processes of Risk and Earned Value are integrated in what
practical ways?
_____ a). EV metrics related to Variance and Performance Indices indicate potential risks.
_____ b). IPMR reporting requirements include explicitly addressing risk in Format 5
_____ c). The “Risk Register” is a deliverable artifact in both risk and earned value management
_____ d). All of the above
39. The programmatic management processes of Change Control and Earned Value are integrated in
what practical ways?
_____ a). Any re-baseline of the PMB must follow established change control rules.
_____ b). IPMR reporting requirements include explicitly including corrective actions in Format 5
_____ c). Change control documents are deliverable artifacts in both change and earned value
management
_____ d). All of the above
40. Key indicators for the health and executability of schedule performance include:
_____ a). Baseline Execution Index (BEI) and Critical Path Length Index (CPLI).
_____ b). Schedule Performance Index (SPI) and Schedule Variance
_____ c). Schedule Risk Assessment
_____ d). All of the above
41. Predictive Earned Value Management Metrics include:
_____ a). To Complete Performance Index, TCPIEAC and TCPIBAC
_____ b). Estimate to Complete (ETC) and Estimate at Complete (EAC)
_____ c). Root Cause Analysis using the “5 Whys” technique
_____ d). A and B only
42. Which of the following conditions is not correct.
_____ a). The acronym EV, or Earned Value, is functionally the same as BCWP, or Budgeted Cost
of Work Performed
_____ b). Estimate to Complete (ETC) is the same as Estimate at Complete (EAC)
_____ c). The acronym PV, or Planned Value, is functionally the same as BCWS, or Budgeted Cost
of Work Scheduled
_____ d). The acronym AC, or Actual Costs, is functionally the same as ACWP, or Actual Cost of
Work Performed
43. Earned value measurement techniques allow for discrete measurement of work. The 0/100
technique of measurement is a preferred method because
_____ a). The measurement of the work can be spread over longer time periods, ideally at least 6
Months.
_____ b). Largely irrelevant because it is too granular with respect to measurement.
_____ c). The work is either done or not, ideally within the current reporting month.
_____ d). A and C above.
44. The Critical Path in a schedule can be defined as
_____ a). The determinant of the overall duration of the project as planned (i.e., the shortest time to
complete the project as planned)
_____ b). Where the calculation for Total Float is less than or equal to a specified value, usually zero.
_____ c). The only activities that need to be intensively managed to complete the project/program
_____ d). A and B above.
45. The concept of Float (aka, Slack) includes the following characteristic(s):
_____ a). Total float is the amount of time by which a task on the Critical Path can be delayed
without delaying the finish of the project
_____ b). Free slack is the amount of time (usually calculated in days) by which a task can be
delayed without delaying the schedule for any subsequent task
_____ c). Conceptually, gives an idea for the degree of flexibility in the schedule’s task dependencies
_____ d). All of the above
46. Well-constructed Control Accounts typically have the following attributes.
_____ a). clearly define the measurement technique for each work package
_____ b). are comprised of at least 1 or more work packages, plus planning packages as necessary
_____ c). the intersection of the lowest level of controlling organization where a manager can be
assigned, to the lowest level of WBS element where formal reporting is required.
_____ d). All of the above
Questions 47-50
You are the newly appointed Program Manager of a government software development program.
You are attending your first, quarterly Program Management Review (PMR) with your prime
commercial contractor who is performing a major portion of the effort associated with your total
program. During the PMR, the contractor flashes the slide below which displays information about
the program.
The contractor then asserts, “These are our Earned Value metrics which indicate a highly positive
“Green” status, so there is no need to waste any time on this,” and proceeds to advance to the next
slide. Your Program EV Analyst leans over and whispers to you, “Boss, there are some issues here. I
recommend you go back to the last slide and question the contractor in more detail.”
47. Which one of the following conditions is most likely to apply?
_____ a. The project is ahead of schedule and over-running.
_____ b. The cumulative cost is under-running
_____ c. The EAC is calculated from the cumulative SPI and CPI
_____ d. None of the above
48. Which one of the following conditions is most likely to apply?
_____ a. If the cost performance trend continues, the project will finish ahead of schedule
and under-run budget
_____ b. The EAC is statistically not probable based on the variance between CPI and TCPIEAC.
_____ c. Based on the cumulative actuals, the EAC should be adjusted to $10,612
_____ d. None of the above
49. Which one of the following conditions is most likely to apply?
_____ a. Because the project is ahead of schedule, the EAC will be less than the BAC
_____ b. The earned value metrics are mostly positive and the small variance is easily recoverable by
the next reporting period
_____ c. There is a labor shortage
_____ d. None of the above. The project is over-running.
50. The calculated EAC using a formula that is based on the cumulative cost and schedule
performance indexes is?
_____ a. $10,612
_____ b. $10,429
_____ c. $9,467
_____ d. $9,803
Question 51
Given: The sum of all Work Packages is $3,143.500. All of the work has been planned in detail so
there are no planning packages at any level. There is $65,000 set aside for Management Reserve.
Also, $200,000 is currently being held as Undistributed Budget within the existing Performance
Measurement Baseline. The fixed price contract has a profit/fee of $300,000.
Task: Calculate the Program Budget Elements for the program budget that is diagrammed below (i.e.,
populate the Yellow/shaded boxes where the budget dollar amount $______ is missing).
Question 52
Given:
1. The Network Diagram below with dependency relationships as indicated 2. The Duration for each task
Task: Identify the tasks that are on the Critical Path.
Note 1: You will need to calculate: Early Start, Late Start, Early Finish, Late Finish, and
Float for each task.
Note 2: Populate the empty boxes of standard portrayal of a network diagram.

Having Trouble Meeting Your Deadline?
Get your assignment on EVM Assessment – The program level Integrated Baseline Review completed on time. avoid delay and – ORDER NOW